Notice of Hearing/Ordinance – Hear complaints about the proposed 5 year Capital Improvement Plan

NOTICE

NOTICE IS HEREBY GIVEN that a Public Hearing will be held by the City Council of the City of Monroe, Louisiana, at its regular meeting place, the Council Chamber, City Hall Building, Monroe, Louisiana, Tuesday, April 12, 2022, beginning at 6:00 p.m., to hear and consider all comments, protests and objections relative to the following proposed 5 year Capital Improvement Plan for the City of Monroe.

FIVE YEAR CAPITAL IMPROVEMENT PLAN
FOR THE FIVE YEARS ENDED APRIL 30, 2027
PREPARED FOR BUDGET YEAR 2023

FOR THE YEAR ENDED APRIL 30,

PROJECT NAME RESPONSIBLE DEPARTMENT TOTAL COST 2023 2024 2025 2026 2027
Street Improvements
..........Maintenance Public Works (PW) On going $1,500,000 $1,500,000 $1,500,000 $1,500,000 $1,500,000
..........Hwy. 165 Connector - Phase I Eng $3,580,000 2,000,000 1,500,000
..........Bridge Replace/Rehab/Repair-Multi/Sites Eng 5,600,000 1,300,000
..........Various overlay project 4,300,000 1,000,000 2,000,000 1,000,000
Total Street Proj. 13,480,000 3,800,000 3,500,000 2,500,000 3,500,000 3,000,000
Sewer Improvements - -
..........Citywide I&I study 450,000 200,000 250,000 -
..........Close Oxidation Pond at MLU 1,000,000 200,000 800,000
..........Rehab trunk lines to reduce I&I 2,000,000 100,000 900,000 1,000,000
..........Equalization Basin Rehab Eng/PW 4,000,000 500,000 2,000,000 1,500,000
Total Sewer Proj. 7,450,000 1,000,000 3,950,000 2,500,000 0 0
Drainage Improvements
..........Georgia St. PS/Parker Ditch - Statewide Flood Program(SFP) Eng/PW 5,430,000 200,000 2,700,000 2,230,000
..........Calypso PS Eng/PW 2,900,000 50,000 150,000 300,000 1,400,000 1,000,000
..........Oregon Trail protection levee Eng/PW 1,500,000 450,000 1,000,000
..........Youngs Bayou Retention Eng/PW 6,867,000 200,000 600,000 2,000,000 2,000,000 2,000,000
Total Drainage Proj. 16,697,000 900,000 4,450,000 4,530,000 3,400,000 3,000,000
Water Improvements
..........Hwy 165 Tank & Main PW 4,370,000
..........Treatment Plant Expansion & Renovation PW 45,000,000 20,000,000 20,000,000 5,000,000
..........Water Distribution System Improvements 17,000,000 750,000 750,000 750,000 750,000 750,000
Total Water Proj. 66,370,000 20,750,000 20,750,000 5,750,000 750,000 750,000
Fire Improvements
..........5 new pumper trucks Fire 2,600,000 150,000 1,225,000 1,225,000
Total Fire Proj. 2,600,000 150,000 1,225,000 1,225,000 0 0
Sidewalk & lighting projects
..........Enhance Gr - DeSiard Eng/PW 750,000 500,000 250,000
..........Enhance Gr - Ph 2 Louisville Eng/PW 1,698,000 698,000 500,000 500,000
..........Enhance Gr - Jackson St Eng/PW 1,022,200 1,022,200
..........Enhance Gr - Winnsboro Rd Eng/PW 1,022,200 522,200 500,000
Total Capital Proj. 4,492,400 2,044,400 1,448,000 500,000 500,000 0
Airport Projects
..........Runway Extension Airport 8,000,000 1,600,000 1,600,000 1,600,000 1,600,000
..........Taxiway Realignment Airport 12,000,000 2,400,000 2,400,000 2,400,000 2,400,000 2,000,000
Total Airport Proj. 20,000,000 4,000,000 4,000,000 4,000,000 3,600,000 2,000,000
I-20
..........I-20/Garrett - Kansas Connector Eng 35,000,000 1,500,000 3,500,000 10,000,000 10,000,000 9,000,000
..........Kansas Lane Connector Eng 30,000,000 6,000,000 10,000,000 8,000,000 800,000
..........Frontage Road Projects I-20 13,500,000 3,000,000 3,000,000 2,000,000 1,260,000
Total I-20 Proj. 78,500,000 10,500,000 16,500,000 20,000,000 12,060,000 9,000,000
Total for all Projects $209,589,400 $43,144,400 $55,823,000 $41,005,000 $23,810,000 $17,750,000

NOTICE IS FURTHER GIVEN that copies of the proposed Capital Improvement Program is on file in the City Clerk’s Office, 2nd floor, City Hall Building and can be examined by the public during regular business hours Monday through Friday.

All persons who wished to comment, protest or object to any portion of the above mentioned proposed program is urged to attend this meeting.

NOTICE PUBLISHED IN THE MONROE NEWS-STAR ON MARCH 25TH & APRIL 1ST, 2022.

 

CAROLUS S. RILEY, CMC, MMC

City Clerk